Ahead of Scottish Budget day on Thursday 3 December, this blog series explains how the budget works.
We start with the budget cycle itself: how the budget is developed, scrutinised and approved.
Over the next week, further blogs will explain how the Scottish Budget is funded, how money is spent, and what the Scottish Government can borrow to support its spending plans.
The budget is a process, not an event
The current Scottish Budget process was introduced following a joint review by the Scottish Government and Scottish Parliament in 2017.
The aim was to improve transparency, strengthen scrutiny and make the process better suited to a Parliament with new tax and social security powers.
The outcome of that review led to the process we have today.
Although budget day brings much excitement (well, for some of us), the budget cycle continues year-round.
The process begins before budget day
Because the Scottish Government’s funding is heavily influenced by UK Government decisions, the Scottish Government can’t publish a budget until after the UK Budget.
At the same time, public bodies, local authorities and others need certainty about their funding before the financial year begins in April.
This leaves a narrow window, both for the Scottish Government to publish a budget, and for Parliament to scrutinise it.
For this reason, the budget cycle is front loaded.
The Scottish Government should plan ahead, so that the direction of travel for public spending priorities over the medium term is set out in advance.
And the Scottish Parliament should embed budget scrutiny year-round, aiming to influence budget proposals as they’re being developed – not waiting until after they’ve been published.
So, let’s walk through the different stages of the Scottish Budget cycle.
The Medium-Term Financial Strategy
If the process runs to plan, the Scottish Government should publish its Medium-Term Financial Strategy (MTFS) in May or June. This should inform parliamentary scrutiny by setting out the government’s budgetary priorities for the next five years.
In 2017, the joint review stated that the Scottish Government should include:
- Scottish Fiscal Commission (SFC) forecasts of revenue and demand-led spending (eg. social security spending).
- Broad financial plans for next five years.
- Clear policies and principles for using, managing and controlling the new financial powers.
- Scenario plans to assess the potential impact of various scenarios on the budget.
Due to the 2026 election, the last MTFS was published in June 2025. There have been other occasions where events have led to the MTFS being delayed or cancelled.
Pre-budget scrutiny
Also in May or June, Parliament’s committees usually agree their approach to budget scrutiny for the coming year.
This means they’ll agree which stakeholders they want to hear from and what themes they want to discuss. They might issue a public call for views over the summer.
In September and October, committees tend to hold pre-budget evidence sessions.
They will then issue a report or letter to government at least six weeks before the Scottish Budget is published. This report can draw on evidence a committee has obtained across the entire session of Parliament.
The joint review recommended that committees’ pre-budget reports include views on the delivery and funding of existing policy priorities, any proposed changes and how these should be funded, and the impact of spending on the delivery of outcomes.
This is the opportunity for committees to influence budget proposals. Clear and specific recommendations are likely to have the most impact. Pre-budget reports also give committees an opportunity to press the government for evidence to support its tax and spending choices.
UK Budget
Usually in October or November, the UK Government publishes its proposed budget for the coming financial year. Decisions at the UK Budget have a direct impact on the Scottish Budget, as they can result in Barnett consequentials which add to the Scottish Government’s block grant funding.
Once the UK Budget is published, the SFC will begin to finalise its forecasts for the Scottish economy and the forthcoming Scottish Budget’s tax measures and social security spending.
Scottish Budget
Usually in December, but sometimes in early January, budget day arrives. The Scottish Government publishes its proposed budget for the coming financial year.
This includes a summary of how parliamentary committees have influenced the formulation of the Budget.
Ministers will provide a more detailed written response to individual committees’ pre-budget reports or letters within five sitting days of the Budget being published. Committees typically invite their respective Ministers to give oral evidence on the response received.
The Budget Bill
After publishing its budget proposals, the Scottish Government then introduces the Budget Bill. If passed, this gives the Scottish Government the statutory authority to spend public money as set out in its budget.
The Budget Bill follows the same three stage process as other Bills. There are some procedural differences, perhaps the main one being that only members of the Scottish Government can propose amendments at Stage 2. However, these amendments can reflect proposals brought forward by committees or Members of other parties.
Proposed income tax rates and bands are not part of the Budget Bill. They are set out by the Scottish Government in a “Scottish rate resolution” (SRR). Parliament votes on the SRR before Stage 3 of the Budget Bill. If the SRR is not passed, the Budget Bill cannot proceed to Stage 3.
The Budget Bill is usually passed in February ahead of the financial year beginning in April.
In-year revisions
As the financial year progresses, plans and economic conditions might change.
For example, additional funding might become available to the Scottish Government if the UK Government increases in-year spending in devolved areas.
So, the Scottish Government can propose changes to its budgeted spending plans midway through the financial year.
In-year revisions typically happen twice – the Autumn Budget Revision usually happens in September and the Spring Budget Revision in late January or early February. There is the option for a third budget revision, but this rarely happens.
Transfers of funding between individual entities that are named in the Budget Bill (by now, the Budget Act) need the approval of Parliament, as well as transfers between portfolios that are either:
- above £75 million in 2016 prices, or
- greater than 15% of the portfolio total.
In-year revisions are enacted via a Scottish Statutory Instrument (SSI), which amend the statutory spending limits in the Budget Act.
The Finance and Public Administration Committee consider budget revisions and report to Parliament. Parliament must then pass a resolution for the SSI to be enacted.
Outturn data
By the end of March, the financial year has passed but the budget cycle continues.
Budgets are based on forecasts. Outturn data shows what actually happened.
This matters because differences between forecasts and actual outturn can affect future budgets:
- If the Scottish Government underspends compared to its budgeted spending limits, it can use the Scotland Reserve to carry money forward into the next financial year.
- Tax revenues can be higher or lower than forecast. Differences are applied to future budgets, in what’s known as a ‘reconciliation’.
- Borrowing may differ from what was planned, leaving more or less headroom against the Scottish Government’s borrowing limits in future years.
Outturn data is published in three publications:
- The Scottish Budget Final Outturn Report in June, which details outturn spending compared to the spending limits authorised by Parliament.
- The Fiscal Framework Outturn Report in September, which details tax revenues, social security spending, Block Grant Adjustments and Scottish Government borrowing compared to what was forecast when the budget was set.
- The Consolidated Accounts towards the end of Autumn, which are essentially the Scottish Government’s audited financial statements.
This Fiscal Framework Outturn Report takes its name from the agreement between the UK and Scottish Governments that underpins the Scottish Budget’s funding arrangements. We’ll explore this in the next blog – how the Scottish Budget is funded.
Rob Watts, Senior Researcher, Financial Scrutiny Unit, SPICe